Technical Information |
|
Substrate | Min. 64mm steel / timber stud wall with a minimum of two layers of 13mm (or greater) FR plasterboard on each side, with or without insulation.
Min. 116mm concrete wall/masonry wall/block wall |
AGNI-Box services | DN25mm copper pipe with Armaflex insulation
DN50mm copper pipe with Armaflex insulation DN32mm PP-R pipe DN32mm C-PVC pipe |
Annular gap | 0 - 5mm |
AGNI-Products | AGNI-Box, AGNI-Seal |
Protection installation | Both sides of the wall |
Compliance Information |
|
Standards | AS1530.4-2014, AS4072.1-2005 |
AGNI-Box system FRL/FRR | -/120/90 |
AGNI-Box services FRL/FRR | DN25mm copper pipe with Armaflex insulation -/120/90
DN50mm copper pipe with Armaflex insulation -/120/90 DN32mm PP-R pipe -/120/120 DN32mm C-PVC pipe -/120/120 |
Reference | PF24126 |